BikeWalkLee transmits its comments to BoCC on transportation projects to be debated on Monday. If you want to share your views with commissioners, this is the week.
At Monday's June 3rd Management and Planning (M and P) meeting, the County Commissioners will have their second discussion about three transportation projects on the draft CIP. Click here for the background materials for this meeting (Agenda Item #2).
In BikeWalkLee's May 26th blog, we reported on the Lee County Advisory Committees' recommendations on these transportation projects. Today, BikeWalkLee sent a letter to the Commissioners on its comments and recommendations for consideration at Monday's meeting.
6/18 update: News-Press 6/18 article: Alico Road widening stirs debate: Is Lee County jumping the gun?
Below is the e-mail to BoCC transmitting our letter, which summarizes our recommendations:
May 30, 2013
County Commissioners,
Attached is BikeWalkLee's letter to the Board for Monday's M
& P meeting, which contains our comments and recommendations on the
transportation component of the draft CIP. Our letter asks that you
consider these issues in the larger context of the fiscal realities facing
transportation funding.
This letter is organized around projects in the CIP and
includes as attachments our previous recommendations, as well as those of the
LPA and CSAC Committees. We believe that implementing these
recommendations would allow the Board members and the County to realize the
goal of fiscal responsibility and community livability.
Below is the summary of BikeWalkLee's specific CIP
recommendations related to the issues before you on Monday's agenda:
Estero Boulevard: Estero Boulevard should be
considered as the county's top priority project and funds should be reallocated
to fully fund the second segment ($7 M) over the next two years.
Alico Road: The Alico Road project should not move
forward until a comprehensive master plan for the Research Diamond area is
completed.
·
The $1.6 million budgeted for 2012-13 for the
design phase as well as the proposed $8.35 M in the 2015-16 and the $0.5 M
2016-17 amount be reallocated to the Estero Blvd. project (a total of $10.6
million).
·
When/if this road is ready for widening, the
costs should be paid for by benefiting land owners/developers, not by county
residents through gas taxes.
Homestead Road: The
Homestead Road Complete Streets study now underway should be completed (scheduled
for June 2014) before making further decisions on the Homestead Road project
(Sunrise Blvd. to Alabama Rd ).
·
A portion of the $3 million currently available
for ROW purchases should be reallocated to street redesign and the remaining
funds for ROW purchases should be expended subsequent to the needs outlined in
the redesign.
·
Funds budgeted in 2015-16 should be dedicated to
redesign and construction costs (now in 2015-16 for $12.1 M) should be moved to
2016-17.
Ortiz Avenue: The Ortiz
north of Ballard should be redesigned as a two-lane section with a turn
lane/median and other complete street features.
·
A portion of the $3.1 million currently
available for ROW purchases should be reallocated to street redesign and the
remaining funds for ROW purchases should be expended subsequent to the needs
outlined in the street redesign.
·
The $10.7 million in CIP budget in the 6-10 year window should be revised to accurately reflect the
costs of the redesigned street.
The county's approach to
transportation planning and budgeting needs a major overhaul in light of
revenue realities. BikeWalkLee recommends that the Board hit the
"pause" button, and do what other communities around the country are
starting to do--take all the projects in the pipeline and re-evaluate them,
right-size them, focus on improving existing roadways instead of building new
capacity, work closely with their communities, and re-prioritize our
transportation investments to live within the funds available.
Thank you for considering our recommendations as you set
budget priorities for next year and beyond.
Darla Letourneau & Margaret Banyan
on behalf of BikeWalkLee